PMP考试每天一练-2020年PMP考试练习题150
PMP考试练习题一: A project manager discovers a key feature of the deliverable deviates from the customer’s original specification, but meets quality and legal requirements. With budget and schedule constraints team members suggest keeping the original design, while other team members insist on modifying the design to meet the customer’s requirement. After negotiation, the final decision is to keep the current design.The project manager should take which of the following actions next? A. Follow the risk response matrix B. Change the quality plan C. Update scope management plan D. Follow the change management procedure 项目经理发现可交付成果的一个关键功能与客户的原始技术规定存在偏差,但是满足质量和法律要求。在预算和进度都有制约的情况下,一些团队成员建议保留原始设计,而另一些团队成员坚持改变设计,满足客户的需求。协商之后,最终决定还是保留当前设计。项目经理下一步应该采取下列哪一项措施? A. 遵循风险响应矩阵 B. 变更质量计划 C. 更新范围管理计划 D. 遵循变更管理程序 PMP考试答案解析:虽然满足法律和质量要求,但是“关键功能与客户的原始技术规定存在偏差”,与原始相比是有变化的。遵循变更管理流程。 PMP考试参考答案:D PMP考试练习题二 The project is half way to completion and continues to be over budget. The current project metrics are as follows: Schedule Performance Index (SPI) =0.96 Cost Performance Index (CPI) =0.98 Actual Cost (AC) =500,000 Budget at Completion (BAC) =1,000,000 Which of the following is the expected total cost of completing all work? A. US$1, 505, 024 B. US$1, 101, 666 C. US$1, 020, 408 D.US$990,073 项目处于完工中途,并继续超出预算。当前的项目指标如下: 进度绩效指数(SPI)=0.96 成本绩效指数(CPI)=0.98 实际成本(AC)=500,000 完工预算(BAC)=1,000,000 下列哪一项属于完成全部工作的预计总成本? A. US$1,505,024 B. US$1,101,666 C. US$1,020,408 D. U$990,073 PMP考试答案解析:典型偏差:EAC=BAC/CPI=1000,000/0.98=1020408 PMP考试参考答案:C |