PMP考试每天一练-2020年PMP考试练习题150

转载者:PMP团购网      发布时间:2020/11/13        点击: 2007

PMP考试练习题一:

A project manager discovers a key feature of the deliverable deviates from the customer’s original specification, but meets quality and legal requirements. With budget and schedule constraints team members suggest keeping the original design, while other team members insist on modifying the design to meet the customer’s requirement. After negotiation, the final decision is to keep the current design.The project manager should take which of the following actions next?

A. Follow the risk response matrix

B. Change the quality plan

C. Update scope management plan

D. Follow the change management procedure

项目经理发现可交付成果的一个关键功能与客户的原始技术规定存在偏差,但是满足质量和法律要求。在预算和进度都有制约的情况下,一些团队成员建议保留原始设计,而另一些团队成员坚持改变设计,满足客户的需求。协商之后,最终决定还是保留当前设计。项目经理下一步应该采取下列哪一项措施?

A. 遵循风险响应矩阵

B. 变更质量计划

C. 更新范围管理计划

D. 遵循变更管理程序

PMP考试答案解析:虽然满足法律和质量要求,但是“关键功能与客户的原始技术规定存在偏差”,与原始相比是有变化的。遵循变更管理流程。

PMP考试参考答案:D

PMP考试练习题二

The project is half way to completion and continues to be over budget. The current project metrics are as follows: Schedule Performance Index (SPI) =0.96 Cost Performance Index (CPI) =0.98 Actual Cost (AC) =500,000 Budget at Completion (BAC) =1,000,000 Which of the following is the expected total cost of completing all work?

A. US$1, 505, 024

B. US$1, 101, 666

C. US$1, 020, 408

D.US$990,073

项目处于完工中途,并继续超出预算。当前的项目指标如下:

进度绩效指数(SPI)=0.96

成本绩效指数(CPI)=0.98

实际成本(AC)=500,000

完工预算(BAC)=1,000,000

下列哪一项属于完成全部工作的预计总成本?

A. US$1,505,024

B. US$1,101,666

C. US$1,020,408

D. U$990,073

PMP考试答案解析:典型偏差:EAC=BAC/CPI=1000,000/0.98=1020408

PMP考试参考答案:C

阅读本文的人还阅读了:
PMP考试时间及报名时间
本科结业可报考pmp吗?
pmp是什么岗位?
pmp考试时间2021年
厦门PMP考试地点在哪里?
pmp证书含金量如何?
PMP考试费用为什么这么贵?


合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库