PMP考试每天一练-2020年PMP考试试题43

转载者:PMP团购网      发布时间:2020/4/1        点击: 1868

PMP考试试题一:

A project team will receive a bonus for completing early. The project manager realizes the project can be completed early if the subcontractor delivers a key component early. The project manager authorities a bonus for the subcontractor for delivering the key component early.Which strategy is the project manager using to deal with the bonus?

A.Exploit

B.Share

C.Mitigate

D.Fast track

项目团队提前完工将获得奖金。项目经理意识到如果分包商能提前交付某个关键部件,则项目可以提前完工。项目经理为分包商提前交付关键部件提供奖金。项目经理采用了什么策略来处理奖金?

A.开拓

B.分享

C.减轻

D.快速跟进

PMP答案解析:分享奖金,把机会外包出去。

PMP参考答案:B

PMP考试试题二

A project manager suspects there is a quality defect in a recently produced batch of products. However, a test for this defect will be destructive to the products. What should the company do next'?

A. Execute a design of experiments on the batch of products.

B. Randomly select units from the batch to measure the extent of the defect.

C. Execute statistical sampling with pre-defined acceptance criteria.

D. Release the current batch to sell at a discounted price,

项目经理怀疑最近生产的产品批次中存在一个质量缺陷。但是,对这个缺陷执行测试对产品将是破坏性的。公司下一步应该怎么做?

A.对该产品批次执行实验设计。

B.从产品批次中随机选择几组来测量缺陷的范围。

C.使用预先定义的验收标准执行统计抽样

D.发布当前批次产品,按打折价销售。

PMP答案解析:PM怀疑存在质量缺陷,对缺陷执行测试又具有破坏性,那就从产品中选出一些样品来进行测试。

PMP参考答案:C

阅读本文的人还阅读了:
pmp考试含金量多少?
pmp证书挂靠一年多少钱?
pmp证书含金量如何?
PMP考试费用为什么这么贵?
参加PMP考试需要多少费用?
pmbok第六版免费下载
pmbok第六版英文版 pdf

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库