PMP考试每天一练-2020年PMP考试试题33

转载者:PMP团购网      发布时间:2020/3/11        点击: 1360

PMP考试试题一:

A project’s expected duration is seven weeks. However, several stakeholders will not be available at this time due to vacations.What should the project manager do next?

A.Assess the impact of moving forward with the project

B.Put the project on hold until the stakeholders return

C.Update the resource calendar

D.Escalate the issue to senior management

一个项目的预算持续时间为七周。但是,由于假期原因,多名干系人此时都不在。项目经理下一步该怎么做?

A.评估将项目向前推进的影响

B.暂停项目,直至干系人回来为止

C.更新资源日历

D.将问题上报给高级管理层

PMP答案解析:资源日历表明了资源的工作时间和非工作时间。

PMP参考答案:C

PMP考试试题二

A team member with key technical skills disagrees with the way in which the project is managed. What should the project manager do first?

A. Meet with the team member privately to discuss the issue.

B. Continue with the project because it will not affect the project’s progress.

C. Acknowledge the team member’s contributions and ability on the project

D. Address the. Team member’s issue in a team meeting

一名拥有关键技术技能的团队成员对项目管理方式不认同。项目经理首先应该怎么做?

A.与该名团队成员私下讨论该问题。

B.继续项目,因为这不影响项目进度。

c.认可团队成员对该项目的贡献和能力。

D.在团队会议上解决团队成员的问题。

PMP答案解析:团队成员对PM的项目管理方式不认同,说明有冲突,最好的冲突解决方法合作解决问题。

PMP参考答案:A

阅读本文的人还阅读了:
2020年PMP报名资格是什么?
2020年pmp报名官网是什么?
2020年pmp报名时间是什么?
PMP认证的含金量如何?
pmp挂靠一年多少钱?
PMP证书可以挂靠吗?
PMP考试通过率多少?
PMP考试多少分及格?
PMP通过率高吗?
PMP通过率怎么样?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库