PMP考试每天一练-2020年PMP考试试题21
PMP考试试题一: Due to quality control issues, a project is behind schedule. There is no obvious pattern to the identified defects. Using a qualitative approach, which quality control tool should be used to determine the source of the defects? A. Histogram B. Pareto chart C. Scatter diagram D. Cause and effect diagram 由于质量控制问题,项目落后于进度。没有识别缺陷的明显模式。使用定性方法,应使用哪一种质量控制工具来确定缺陷来源? A.直方图 B.帕累托图 C.散点图 D.因果图 PMP答案解析:找原因、找缺陷来源用因果图。 PMP参考答案:D PMP考试试题二 During project implementation, a critical item is delivered late because a customer’s safety requirement was not considered. This late delivery impacts the project team’s working hors The project manager should first identify this constraint in which of the following documents? A.Project management plan B.Resource management plan C.Risk register D.Project charter 在项目实施期间,由于未考虑客户的安全要求,一个关键项延迟交付。该延迟交付影响了项目团队的工作时间。项目经理应事先在下面那一份文件中识别该制约因素? A.项目管理计划 B.资源管理计划 C.风险登记册 D.项目章程 PMP答案解析:项目章程中包含了制约因素。 PMP参考答案:D |