PMP考试每天一练-2020年PMP考试试题19
PMP考试试题一: The project expects critical equipment shipped from a foreign country to arrive by a scheduled date. However, there is severe weather along the shipment route. Severe weather was previously identified as a risk. A team member is concerned the equipment will not arrive on time.Which should the project manager do next? A.Execute the contingency plan in the risk management plan B.Schedule a team meeting to update the risk register and risk treatment C.Submit the change request to the change control board for corrective actions D.Contact the shipping company to obtain a definite delivery date 项目团队预期从国外发运的关键设备将按照预期计划日期抵达。但是,在运输途中发生恶劣天气。恶劣天气之前已被识别为一项风险。一名团队成员担心设备不会按时抵达。项目经理下一步该怎么做? A.执行风险管理计划中的应急计划 B.安排一次团队会议,更新风险登记册和风险处理 C.向变更控制委员会提交变更请求获得纠正措施 D.联系运输公司获得确定的交付日期 PMP答案解析:恶劣天气风险之前已被识别,直接执行应急计划即可,执行应急计划要提出变更请求。 PMP参考答案:C PMP考试试题二 A project manager is assigned to a project to replace an outdated system. During installation the equipment is damaged and requires technical resources to repair it. What document must be updated to communicate this occurrence with the stakeholders? A. Issue log B. Status report C. Incident management plan D. Resource allocation matrix 项目经理被任命管理一个更换过时系统的项目。在安装期间,设备损坏,并要求技术资源修理。必须更新哪一份文件将这种情况与干系人沟通? A.问题日志 B.状态报告 c.事件管理计划 D.资源分配矩阵 PMP答案解析:用问题日志记录由谁负责在目标日期内解决特定问题,并监督解决情况。 PMP参考答案:A |