PMP考试每天一练-2020年PMP考试试题17
PMP考试试题一: The stakeholders request the project manager report indirect and direct costs separately. Which of the following is a direct cost? A.Telephone service costs B.Training for a duty required by the project C.Jury duty pay D.Employee salary 项目干系人要求项目经理分别报告间接成本和直接成本。以下那一项属于直接成本? A.电话服务成本 B.项目需要的岗位培训 C.陪审员义务支付 D.员工工资 PMP答案解析:看英文理解为此项目需要的岗位培训。 PMP参考答案:B PMP考试试题二 Aproject manager completes development of the project management plan. Approval is obtained from all the key stakeholders, with the exception of the sates manager. Should the project manager proceed with project execution? A. No; the project manager should complete a risk register and escalate to the project sponsor. B. No; the project manager should continue to follow the process and obtain the sales manager's approval, C. Yes; the project manager should proceed and inform the project sponsor of the situation. D. Yes; the project manager should proceed to avoid delay, and follow up with the sales manager as soon as possible. 项目经理完成项目管理计划的制定。已经获得除销售经理以外的所有关键干系人批准。项目经理是否应继续执行项目? A.否:项目经理应完成一份风险登记册,并上报给项目发起人。 B.否:项目经理应继续遵循过程,并获得销售经理的批推。 C.是:项目经理应继续并将情况通知项目发起人。 D.是:项冒经理应继续,以避免延期,并尽快与销售经理跟进。 PMP答案解析:项目管理计划制定后应该获得关键干系人的批准后才可执行。 PMP参考答案:B |