PMP考试试题一:

The stakeholders request the project manager report indirect and direct costs separately. Which of the following is a direct cost?

A.Telephone service costs

B.Training for a duty required by the project

C.Jury duty pay

D.Employee salary

项目干系人要求项目经理分别报告间接成本和直接成本。以下那一项属于直接成本?

A.电话服务成本

B.项目需要的岗位培训

C.陪审员义务支付

D.员工工资

PMP答案解析:看英文理解为此项目需要的岗位培训。

PMP参考答案:B

PMP考试试题二

Aproject manager completes development of the project management plan. Approval is obtained from all the key stakeholders, with the exception of the sates manager. Should the project manager proceed with project execution?

A. No; the project manager should complete a risk register and escalate to the project sponsor.

B. No; the project manager should continue to follow the process and obtain the sales manager's approval,

C. Yes; the project manager should proceed and inform the project sponsor of the situation.

D. Yes; the project manager should proceed to avoid delay, and follow up with the sales manager as soon as possible.

项目经理完成项目管理计划的制定。已经获得除销售经理以外的所有关键干系人批准。项目经理是否应继续执行项目?

A.否:项目经理应完成一份风险登记册,并上报给项目发起人。

B.否:项目经理应继续遵循过程,并获得销售经理的批推。

C.是:项目经理应继续并将情况通知项目发起人。

D.是:项冒经理应继续,以避免延期,并尽快与销售经理跟进。

PMP答案解析:项目管理计划制定后应该获得关键干系人的批准后才可执行。

PMP参考答案:B

阅读本文的人还阅读了:
pmp远程课程费用大概是多少?
PMP远程考试费用多少?
PMP远程和面授的考试费用一样吗?
PMP远程培训的优势?
pmp可以远程授课吗?
PMP远程班有用吗?
报PMP远程班,可参加PMP考试吗?

留言讨论区
我也来说两句


获取更新

合作与联系

友情链接: PMP培训团购网 安徽成考网 健身教练培训 项目管理者联盟 天津坦途教育网 磨石建筑教育 光环国际 德学培训网 湖南自考 中公考研网校 上学 托福 广东自考
PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
东北PMP团购
其他城市团购
PMP团购网
PMP在线课程(点击)