以下城市均已开通:
关闭
当前位置:PMP团购网 > PMP考试资料 > 正文

PMP考试每天一练-2019年PMP考试试题135

转载者:PMP团购网      发布时间:2019/10/8        点击: 1341

PMP考试试题一:

Two project team members consistently disagree and criticize each other during team meetings, which negatively affects the team. What should the project manager do?

A. Meet with these team members to help them find common ground.

B. Take no action, since this is not affecting the project's cost or schedule.

C. Initiate a team-building exercise for the project team.

D. Reassign one of these team members to another project.

两名项目组成员一直持有不同意见,并在团队会议上批评对方,对团队产生负面影响。项目经理应该怎么做?

A.与这两名团队成员开会,帮助他们找到共同点。

B.不采取任何行动,因为这是不影响项目的成本或进度。

C.为项目团队发起一项团队建设练习。

D. 将其中一名团队成员重新分配到另一个项目

PMP答案解析:四个选项中A为最优选项。

PMP参考答案:A

PMP考试试题二

During a new system deployment, a company plans quality management. Which of the following quality control activities should be included in this process?

A. Audit the technical requirements for the system's specifications

B. Perform a process analysis to identify issues and plan preventive actions

C. Produce a checklist to verify that a set of required steps were performed

D. Examine whether the team is using best practices throughout the project

在一个新系统部署期间,公司制定质量管理计划,下列哪一个质量控制活动应包含在这个过程中?

A.审计系统技术规范的技术要求

B.执行过程分析,识别问题并计划预防措施

C.制作一份核对表,核实已执行一系列必要的措施

D.检查团队在项目过程中是否使用最佳实践

PMP答案解析:A是质量控制,BCD都是质量保证。

PMP参考答案:A

阅读本文的人还阅读了:
PMP考试试题是什么样?
PMP考试题型是什么?
PMP考试内容是什么?
高中或以下学历可以考PMP吗?
大专可以考PMP吗?
英语不好可以考PMP吗?
PMP证书与学历挂钩吗?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库