PMP考试每天一练-2019年PMP考试试题120

作/转载者:PMP团购网      发布时间:2019/9/24        点击: 182

PMP考试试题一:

During project execution, a project manager discovers that a client manager is repeatedly unresponsive to vital communications that directly affect the project. After holding several meetings with this manager and updating the issue log, the situation has not improved. What should the project manager do next?

A. Notify the client that the project will be paused until a response is received.

B. Issue formal correspondence to the client, and continue running the project.

C. Issue formal correspondence to the client, and escalate the problem to the project sponsor.

D. Inform the project sponsor that the project is being hindered by the client manager.

在项目执行期间,项目经理发现客户经理对直接影响项目的重要沟通一直不响应。在与该经理召开多次会议并更新问题日志之后,问题未得到改进。项目经理下一步应该怎么做?

A.通知客户将暂停该项目,直到收到响应。

B.向客户发出正式通知,并继续运行该项目。

C.向客户发出正式通知,并将该问题上报给项目发起人。

D.通知项目发起人,项目受到客户经理的阻碍。

PMP答案解析:本题考点不是非常清晰,四个答案中推荐C答案,向客户发出正式通信是正式书面沟通,上报发起人是因为超过项目经理管理权限的问题需要上报给发起人

PMP参考答案:C

PMP考试试题二

During project planning, the project team collects cost estimates, the delivery of major components, and specific engineering durations. To calculate a distribution of possible outcomes

A.Schedule network analysis

B.Monte carol simulation

C.Critical path method

D.Resource leveling

在项目规划期间,项目团队收集成本估算、交付主要部件以及具体工程设计时间。若要计算整个项目的可能结果分布,项目团队应使用什么技术?

A.进度网络分析

B.蒙特卡洛模拟

C.关键路径法

D.资源平衡

PMP答案解析:制定进度计划的工具蒙特卡洛分析。

PMP参考答案:B

阅读本文的人还阅读了:
PMP考试题型是什么?
PMP考试内容是什么?
PMP考试有题库吗?
深圳PMP考试地点在哪里?
香港PMP考试地点在哪里?
青岛PMP考试地点在哪里?

留言讨论区
我也来说两句


获取更新

合作与联系

友情链接: PMP培训团购网 安徽成考网 健身教练培训 项目管理者联盟 天津坦途教育网 磨石建筑教育 光环国际 德学培训网 湖南自考 中公考研网校
PMP团购导航
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
东北PMP团购
其他城市团购
远程PMP团购
PMP团购网
免费领PMP团购券