以下城市均已开通:
关闭
当前位置:PMP团购网 > PMP考试资料 > 正文

PMP考试每天一练-2019年PMP考试练习题110

转载者:PMP团购网      发布时间:2019/9/9        点击: 1380

PMP考试练习题一:

Before finalize the project management plan, project managers considers recording the alternatives on project activities relationship. Which of the following tool should the project manager use to describe activities sequence?

A.Work breakdown structure

B.RACI chart

C.Activity list

D.Project schedule network diagrams

在最终确定项目管理计划之前,项目经理考虑记录项目活动之前关系的替代方案。项目经理应使用什么工具描述活动顺序?

A.工作分解结构

B.RACI图

C.活动清单

D.项目网络图

PMP答案解析:项目网络图就是用来表示项目活动之间关系。

PMP参考答案:D

PMP考试练习题二

Aproject manager identifies four risks and their associated probability and impact on the project's objective, The organization's risk classification guidelines state the following: Based on these guidelines, what risk is medium?

A. A

B. B

C. C

D. D

项目经理识别到四个风险及其相关的概率和对项目目标的影响。组织的风险分类指导如图:基于这个指导原则,哪个风险的等级为中?

A. A

B. B

C. C

D. D

PMP答案解析:图中A所在位置为中等风险。

PMP参考答案:A

阅读本文的人还阅读了:
PMP考试三个月来得及吗?
广州PMP考试地点
PMP考试报名资格怎么审查?
PMP认证培训怎么选机构?
PMP考试有题库吗?
PMP考试报名费是多少?
PMP考试时间一年有几次?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库