以下城市均已开通:
关闭
当前位置:PMP团购网 > PMP考试资料 > 正文

PMP考试每天一练-2019年PMP考试练习题84

转载者:PMP团购网      发布时间:2019/7/15        点击: 1712

PMP考试练习题一:

During a new system deployment, a company plans quality management. Which of the follow quality control activities should be included in this process?

A.Audit the technical requirements for the system’s specifications

B.Perform a process analysis to identify issues and plan preventive actions

C.Produce a checklist to verify that a set of required steps were performed

D.Examine whether the team is using best practices throughout the project

在一个新系统开发期间,公司制定质量管理计划。下列哪一个质量控制应包含在这个过程?

A.审核系统规格的技术要求

B.执行过程分析以识别问题并规划预防措施

C.执行检查表以核实项目按照规定的步骤和流程执行

D.检查团队是否在项目过程中执行良好的做法

PMP答案解析:公司制定质量管理计划,说明正在进行规划质量管理的过程。B、C、D都是在实施质量保证

PMP参考答案:A

PMP考试练习题二

A company's model product has been selling well for many years, but the company now wants to rebrand it to meet developing market demands, During execution, a project team member points out that some older equipment and materials, amounting to US$50,000, need to be scrapped. This was not defined in the project management plan. Who should review and approve this cost threshold?

A. Change control board (CCB)

B. Functional management team

C. Project manager

D. Project management team

公司的模范产品已经畅销多年,但该公司现在想更改品牌名称,以满足市场发展的需求。在执行过程中,项目团队成员指出,需要报废一些较旧的设备和材料,金额为50,000美元。这在项目管理计划中未定义。谁应该审查和批准这个成本门槛?

A.变更控制委员会(CCB)

B.职能管理部门

C.项目经理

D.项目管理团队

PMP答案解析:在项目管理计划中末定义的成本项的变更,属于成本基准的变更,通常由CCB来批准

PMP参考答案:A

阅读本文的人还阅读了:
pmp认证培训费用多少?
pmp项目管理师是什么?
pmp证书是什么?
PMP证书有用吗?
工作年限不够可以考PMP吗?
PMP证书在哪个行业比较有用
PMP的价值在哪?
PMP认证考试的报名条件?
PMP是什么?
PMP考试有什么科目?

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库