PMP考试练习题一: During a project's execution phase, a project manager determines that a criticalscheduled milestone may be missed, What should the project manager do? A. Perform a risk data quality assessment. B. Conduct a risk audit. C. Analyze the risk register. D. Review the risk response plan. 在项目的执行阶段,项目经理确定了一个可能被错过的关键计划里程碑。项目经理应该怎么做? A.执行风险数据质量评估。 B.开展风险审计。 C.分析风险登记册。 D.审查风险应对计划。 PMP答案解析:风险应对计划包含在规划风险应对输出和更新的风险登记册中。 PMP参考答案:C PMP考试练习题二 A project manager’s construction project is on time, on scope and within budget. The project manager teams that a favorable weather forecast will allow for the implementation of critical path activities earlier than expected.What should the project manager do first? A. revise the schedule B. initiate perform integrated change control process C. check risk register D. follow the planned schedule 项目经理的施工项目符合时间、范围以及预算。项目经理了解到有利的天气预报将允许比预期提前执行关键路径上的活动。项目经理首先该做什么? A.修订进度计划 B.开始执行整体变更控制过程 C.检查风险登记册 D.遵循计划的进度计划 PMP答案解析:积极风险,应该先查看风险登记册是否有应对措施。 PMP参考答案:C |