PMP考试每天一练-2019年PMP考试练习题80
PMP考试练习题一: A team member consistently misses task deadlines. What should the project manager do? A. Reprimand the team member. B. Request a project status report from the team member. C.. Remove the team member from the project. D. Conduct a project performance appraisal of the team member. 一名团队成员始终错过任务的期限。项目经理应该怎么做? A.惩戒该团队成员。 B.要求该团队成员提交项目状况报告。 C.将该团队成员从项目中开除。 D.对该团队成员开展项目绩效评价。 PMP答案解析:管理团队过程,通过项目绩效评价对于团队成员提出建设性的反馈 PMP参考答案:D PMP考试练习题二 Which of the following inputs should a project manager use to address a change? A. work performance reports B. approved change requests C. change logs D. change control meetings 项目经理应该使用下列哪一项输入来解决变更? A.工作绩效报告 B.批准的变更请求 C.变更目录 D.变更控制会议 PMP答案解析:考实施整体变更控制的输入 PMP参考答案:A |