PMP考试练习题一: The total budget for a construction project is US$500 million. The management reserve is US$100 million. An unexpected event affects the project's progress. The project sponsor approves the use of US$50 million of the management resented to respond to the event. What is the revised cost baseline? A. US$400 million B. US$450 million C. US$500 million D. US$550 million 施工项目的总预算为5亿美元。管理储备为1亿美元。一个意外事件影响了项目的进度。项目发起人批准使用5000万美元的管理储备来应对该事件。修订后的成本基准是多少? A.4亿美元 B.4.5亿美元 C.5亿美元 D.5.5亿美元 PMP答案解析:成本基准不包括管理储备,所以修订前为4亿美元,经过批准,修订后,管理储备金进入新的成本基准,成为4.5亿美元。 PMP参考答案:B PMP考试练习题二 A web development firm delivers a product to the client on time and 20% over the original budget. The client is currently soliciting bids for a new web project.What should the web development firm’s project manager do during the closure phase to enhance customer relations? A.Request requirements for the new web project B.Conduct a stakeholder analysis C.Meet with the client to review lessons learned D.Implement corrective actions of the budget controlling 一家网络开发公司按时向客户交付产品,但超出原始预算20%。客户目前正在为一个新网络项目投标。若要增强客户关系,网络开发公司的项目经理在收尾阶段应怎么做? A.索取新网络项目的需求 B.进行干系人分析 C.与客户开会,审查经验教训 D.执行预算控制的纠正措施 PMP答案解析:只有C是收尾阶段需要做的 PMP参考答案:C |