以下城市均已开通:
关闭
当前位置:PMP团购网 > PMP考试资料 > 正文

PMP考试每天一练-2019年PMP考试试题75

转载者:PMP团购网      发布时间:2019/6/24        点击: 1666

PMP考试试题一:

A project manager is assembling team and wants to ensure all the cost estimates are accurate. Which of the following tools should be used to ensure accurate estimates?

A. Sensitivity and reserve analysis

B. Pareto diagrams and earned value analysis

C. Cost aggregation and funding limit reconciliation

D. Delphi analysis and expert judgment

项目经理正在组建一个团队,并希望确保所有成本估算都正确。应使用下列哪一项工具来确保估算准确?

A.敏感性和储备分析

B.帕累托图和挣值分析

C.成本汇总和资金限制平衡

D.德尔菲分析和专家判断

PMP答案解析:选项D是估算成本的工具。选项C是制定预算的工具

PMP参考答案:D

PMP考试试题二

A customer asks a project manager to add a protection mechanism for a power supply system currently under construction. This request will incur sizeable costs. However, if this mechanism is not added, it may cause substantial liability and financial risks for future operations teams. What should the project manager do?

A. Solicit expert judgment from all possible channels.

B. Complete a sensitivity analysis to assess potential impact on the project.

C. Conduct a probabilistic analysis.

D. Perform an expected monetary value (EMV) analysis with the assumption of risk-neutral.

客户要求项目经理为一个目前正处于施工的供电系统增加保护机制。这项请求将产生相当大的成本。但是,如果不添加这种机制,它可能会导致未来运营团队产生大量的责任和财务风险。项目经理应该怎么做?

A.从所有可能的渠道征求专家判断。

B.完成敏感性分析,以评估对项目的潜在影响。

C.进行概率分析。

D.在风险中立的假设前提下,执行预期货币价值(EMV)分析。

PMP答案解析:根据题干,四个答案中最好的答案是EMV分析,通过分析给出决策路径

PMP参考答案:D

阅读本文的人还阅读了:
PMP考试报名资格怎么审查?
PMP认证培训怎么选机构?
PMP培训机构是什么?
PMP认证考试需要准备什么?
杭州PMP考试地点在哪里?
苏州PMP考试地点在哪里?
无锡PMP考试地点在哪里?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库