PMP考试每天一练-2019年PMP考试试题42
PMP考试试题一: A project team member disagrees with a customer request because it may negatively affect organizational culture. What should the project manager do? A. Identify project stakeholders, and create a stakeholder management plan. B. Professionally balance the interests of all project stakeholders. C. Use power and politics to obtain project stakeholders' cooperation. D. Confront the project team member about their unprofessional behavior. 项目团队成员不同意客户的请求,因为可能会对组织文化造成负面影响。项目经理应该怎么做? A.识别项目干系人,并创建一份干系人管理计划。 B.专业地平衡所有项目干系人的利益。 C.使用权力和政治因素获得项目干系人的合作。 D.让项目团队成员面对他们的不专业行为。 PMP答案解析:推荐B答案,项目团队成员也是项目干系人,项目管理需要平衡所有干系人的利益 PMP参考答案:B PMP考试试题二 Which one of the following techniques could be used to measure the compliance ofa project to the organizational policies and procedures? A.Benchmarking B.Delphi C.Root cause analysis D.Quality audit 下列哪一项技术可以用于衡量一个项目是否符合组织政策和程序? A.标杆对照 B.德尔菲技术 C.根本原因分析 D.质量审计 PMP答案解析:质量审计用来确定项目活动是否遵循了组织和项目的政策,过程与程序 PMP参考答案:D |