PMP考试试题一:

A project manager discovers that the critical ratio is 0.7. What does this indicate?

A. The cost performance Index (CPI) is better than planned.

B. The CPl is worse than planned

C. The project's progress is worse than planned.

D. The project's progress is better than planned..

项目经理发现临界比是0.7。这说明什么?

A成本绩效指数(CPI)比计划好

B.CPI比计划差

C.项目进展比计划差

D.项目进展比计划好

PMP答案解析:临界比的计算方法是CPI*SPI,临界比等于0.7,说明项目进展不好

PMP参考答案:

PMP考试试题二

After confirming the availability of human resource and obtaining teams for project assignments, the project manager discovers that the resources will not sufficiently meet the project schedule. The project manager meets with a functional manager who agrees to make additional resources available for the duration of the project.What tool or technique does the project manager use?

A.Negotiation

B.Acquisition

C.Pre-assignment

D.Co-location

确认人力资源可用性并获得执行项目任务的团队后,项目经理发现资源不足以满足项目进度计划,项目经理与职能经理开会,职能经理同意为项目工期增加可用资源。项目经理是用的是什么工具或技术

A.谈判

B.招募

C.预分派

D.集中办公

PMP答案解析:“项目经理与职能经理开会”来获得资源,这是谈判

PMP参考答案:A

阅读本文的人还阅读了:
如何挑选pmp培训班?
pmp认证培训费用多少?
pmp项目管理师是什么?
pmp证书是什么?
PMP培训机构是什么?
PMP认证考试需要准备什么?
PMP报名时间是哪天?

留言讨论区
我也来说两句


获取更新

合作与联系

友情链接: PMP培训团购网 安徽成考网 建工团购网 项目管理者联盟 pmp百科 磨石建筑教育 SPC培训 企业管理培训 清晖PMP培训 光环国际 青岛旅行社
PMP团购导航
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
东北PMP团购
其他城市团购
远程PMP团购
PMP团购网
免费领PMP团购券