PMP考试试题一:

A manufacturing team completes installation of a panel for a client's access control system. After a quality check, the project manager discovers multiple issues and submits a. change request. What type of change request is this?

A.Preventive action

B.Defect repair

C.Corrective action

D.Product update

制造团队完成客户访问控制系统的面板安装。经过质量检查,项目经理发现多个问题,并提交变更请求。这属于哪一类型的变更请求?

A.预防措施

B.缺陷补救

C.纠正措施

D.产品更新

PMP答案解析:修正不一致产品或组件的有目的活动,即为缺陷补救

PMP参考答案:B

PMP考试试题二

There is a potential delay in the internal manufacturing of materials. It is decided that part of the materials will be bought from a third-party manufacturer
What should the project manager work on next?

A.select sellers

B.procurement statement of work

C.requirements documentation

D.independent estimates

内部材料制造存在发生延期的可能性。决定部分材料从某一第三方制造商采购。项目经理接下来该做什么?

A.选择卖方

B.采购工作说明书

C.需求文档

D.独立估算

PMP答案解析:决定将工作外包,接下来就要编制采购工作说明书

PMP参考答案:B

阅读本文的人还阅读了:
pmp认证培训费用多少?
pmp项目管理师是什么?
pmp证书是什么?
国内PMP考试通过率有多高?
PMP考试试题是什么样?
PMP考试题型是什么?
PMP考试内容是什么?
PMP考试有题库吗?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库