PMP考试试题一:

Due to a change in governmental regulations, a final product will require an additional feature. A change request to add the feature is discussed and approved within the project.What type of change request is this?

A.corrective action

B.engineering

C.update

D.defect repair

由于政府法规的变化,最终产品将需要增加功能。在项目中已经讨论并批准增加功能的变更请求。这属于哪一种类型的变更请求?

A.纠正措施

B.工程设计

c.更新

D.缺陷补救

PMP答案解析:更新是对正式受控的项目文件或计划等进行的变更,以反映修改或增加的意见或内容

PMP参考答案:C

PMP考试试题二

A company requires the construction of a 200,000 meter industrial factory capable of producing 10,000 units per day. The facility will be located on unimproved property requiring utilities, access roads, and other infrastructure. What does the project manager need to initiate the project?

A.Marketplace conditions and organizational structure

B.Historical information and lessons learned

C.Project charter and stakeholder register

D.High-Level risks and high-level project description

公司要求能够对一个200,000米、每天生产10,000单位的工业厂房施工。该工厂将设在未经利用的地产中,该地产尚不具备公共设施、进出道路和其他基础设施。启动项目时,项目经理需要做些什么?

A.市场条件和组织结构

B.历史信息和经验教训

C.项目章程和干系人登记册

D.高层级风险和高层级项目描述

PMP答案解析:B、C、D三个答案都有选择的可能性,推荐C答案,作为启动项目要做的两个过程

PMP参考答案:C

阅读本文的人还阅读了:
pmp证书是什么?
PMP证书有用吗?
PMP培训机构怎么选择?
国内PMP考试通过率有多高?
PMP考试试题是什么样?
PMP考试题型是什么?
PMP考试内容是什么?
PMP考试有题库吗?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库