PMP考试试题一:

A buyer and seller sign a contract statement of work. The seller completes the work as specified in the contract; however, the buyer is not satisfied with the results.What is the status of the contract?

A.Incomplete

B.Waived

C.Complete

D.Null and void

买方和卖方签署了一份合同工作说明书,卖方按合同规定完成工作。然而,买方却对工作结果不满意。合同状态是什么?

A.未完成

B.放弃

c.完成

D.无效

PMP答案解析:卖方已按合同规定完成了工作,只是买方主观上不满意

PMP参考答案:C

PMP考试试题二

A manufacturing project is under schedule constraints. At the time of delivery, a shipment of components is cancelled, because the components do not meet minimum requirements. In the project management plan, this was identified as a potential liability.The project manager should do which of the following?

A.Refer to the quality management plan and verify whether the quality metrics are appropriate

B.Survey the industry standards and enterprise environmental factors

C.Review the project management plan to create a more realistic schedule

D.Review and follow up on the execution of the planned risk responses

一个制造项目处于进度制约之下。交付时,一大批部件被废弃,因为这些部件未满足最低要求。在项目管理计划中,这被识别为一个潜在责任。项目经理应该采取下列那种措施?

A.参考质量管理计划并确认质量指标是否适合

B.研究行业标准和事业环境因素

C.审查项目管理计划以创建更现实的进度计划

D.审查并跟踪计划风险应对措施的执行

PMP答案解析:a potential liability翻译为潜在的责任、潜在的倾向,可理解为风险

PMP参考答案:D

阅读本文的人还阅读了:
pmp项目管理师是什么?
pmp证书是什么?
PMP证书有用吗?
PMP认证考试需要准备什么?
PMP报名时间是哪天?
PMP考点在哪里?
PMP认证费用多少?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库