PMP考试每天一练-2018年PMP考试试题158
PMP考试试题一: A project manager must report the project’s status to senior manager. Which of the following tools should the project manager use to show the status of the major deliverable? A.Weekly status chart B.Milestone chart C.Control chart D.Gantt chart 项目经理必须向高级管理层报告项目状态。项目经理应使用哪一项工具从较高层次显示主要可交付成果的状态? A每周状态图 B.里程碑图 c.控制图 D.甘特图 PMP答案解析:里程碑图体现出主要可交付成果的状态 PMP参考答案:B PMP考试试题二 A customer rejects a change to a product even though the change control process was followed.What should the project manager do first? A.Perform configuration verification and audit B.Review detailed change control logs C.Audit the change authorizations D.Assess the change control performance 客户拒绝了对产品的一项变更,即使已遵循变更控制过程。项目经理首先应该怎么做? A.执行配置核实和审计 B.审查详细的变更控制日志 C.审计变更授权 D.评估变更控制绩效 PMP答案解析:保证项目的配置项组成的正确性,以及相应的变更都被登记、评估、批准、跟踪和正确实施,从而确保配置文件所规定的功能要求都已实现 PMP参考答案:A |