PMP考试每天一练-2018年PMP考试试题151
PMP考试试题一: During final product testing of a two-year project, an application is scheduled to be implemented within the next month. The project manager discovers that a mandatory deliverable was overlooked in the project management plan; however, the development team states that it will only take 15 days to complete.What should the project manager do? A.Re-validate the scope B.Perform integrated change control C.Adjust the schedule to cover the change D.Perform crashing to meet the deadline 在一个为期两年项目的最终产品测试期间,一项应用程序安排在下个月实施。项目经理发现项目管理计划中忽略了一个强制性可交付成果。然而,开发团队说只需花15天能够完成。项目经理应该怎么做? A. 重新核实范围 B. 实施整体变更控制 C. 调整进度计划包含变更 D. 执行赶工,满足期限要求 PMP答案解析:“忽略了一个强制性可交付成果”,说明与原计划有偏差,需要变更 PMP参考答案:B PMP考试试题二 The most likely cost for an activity is US$2,000. The optimistic cost is US$1,500. The pessimistic cost is US$3,100.What would be the expected activity cost? A.US$2,000 B.US$2,100 C.US$2,300 D.US$3,100 某项活动的最可能成本是2000美元。乐观成本是1500美元。悲观成本是3100美元。那么预期活动成本是多少? A.2000美元 B.2100美元 C.2300美元 D.3100美元 PMP答案解析:三点估算公式:(1500+4*2000+3100)/6=2100 PMP参考答案:B |