PMP考试试题一:

Early in a project's life cycle, a project manager plans to enhance the project's chance of success by building partnerships and coalitions with project stakeholders. What should the project ragger do to achieve this?

A.Create a stakeholders engagement assessments matrix to identify gaps between current and desired engagement levels.

B.Map the interest levels of each stakeholder to the project's objectives.

C.Document and clarify stakeholder roles by developing a responsible, accountable, consult, and inform (RACI) matrix

D.Gather and analyze information on potential stakeholders to determine whose interests should be considered.

在项目生命周期早期,项目经理打算通过与项目干系人建立合作伙伴关系和联合体,提高项目的成功概率。若要实现这一点,项目经理应该怎么做?

A.创建项目干系人参与评估矩阵,识别当前参与程度与所需参与程度之间的差距。

B.将每位项目干系人的利益层级与项目目标映射。

C.通过制定一份执行、负责、咨询和知情(RACI)矩阵记录并澄清干系人的角色。

D.收集并分析潜在干系人的相关信息,确定应考虑谁的利益。

PMP答案解析:A参考答案为制定干系人管理计划,B为干系人分析,C为RACI,D参考答案为识别干系人。题干提示为项目生命周期早期,首先做识别干系人

PMP参考答案:D

PMP考试试题二

During the customer’s final acceptance of deliverables, the project manager encounters opposition from a local group. The project manager’s company conducts a root cause analysis and discovers that the project did not adequately consider environmental factors for the project.During which process should this have been completed?

A.Initiating

B.Monitoring and controlling

C.Planning

D.Executing

在客户最终验收可交付成果期间,项目经理遭遇到其他地方团队的反对意见。项目经理所在公司开展了一次根本原因分析,发现项目并未充分考虑项目的环境因素。这本应该在下列那一个过程中完成?

A.启动

B.监控

C.规划

D.执行

PMP答案解析:项目经理必须在每个过程中考虑组织过程资产和事业环境因素,即使它们没有被明确地列为输入,尽早考虑组织过程资产和事业环境因素

PMP参考答案:A

阅读本文的人还阅读了:
如何挑选pmp培训班?
pmp认证培训费用多少?
pmp项目管理师是什么?
2019年PMP考试时间是什么?
2019年PMP考试费用是多少?
2019年PMP报考条件是什么?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库