PMP考试试题一:

In a matrix organization, an additional resource is required to complete an unfinished task, the project manager requests the resource from a functional manager.To obtain the functional manager’s approval, which of the following should the project manager include in the resource request?

A.Required skills, resource cost, and duration

B.Resource name, start date, and duration

C.Type of activity, start date, and duration

D.Required skills, start date, and duration

在矩阵式组织中,要求一名额外的资源完成未完成的任务。项目经理向职能经理申请该资源。为获得职能经理的批准,项目经理应将下列那一项包含进资源请求中?

A.需要的技能、资源成本和持续时间

B.资源姓名、开始日期和持续时间

C.活动类型、开始日期和持续时间

D.需要的技能、开始日期和持续时间

PMP答案解析:组建项目团队的工具:多标准决策分析,技能、成本、可用性。参考PMBOK

PMP参考答案:A

PMP考试试题二

A project has an eight-month schedule. Based on the table, what should be the new duration to complete the project?

Project length(months) 8. 00

Budget at completion (BAC) US$20000

Actual cost for work performed (ACWP) US$8000 Actual cost (AC)

Budgeted cost for work performed(BCWP) US$7500 Earned value(EV)

Budgeted cost for work scheduled (BCWS) US$8500 Planned Value(PV)

A.1 month

B.8.6 month

C.9.1 month

D.12month

项目工期为八个月。根据表格,完成项目的新工期为多少?

项目工期(月) 8.00

完工预算(BAC) 20000美元

已完工作实际成本(ACWP) 8000美元 实际成本(AC)

已完工作预算成本(BCWP) 7500美元 挣值(EV)

计划工作预算成本(BCWS) 8500美元 计划价值(PV)

A. 1个月

B. 8.6个月

C. 9.1个月

D. 12个月

PMP答案解析:新工期=8/SPI=8*8500/7500=9.1

PMP参考答案:C

阅读本文的人还阅读了:
PMP考试报名资格怎么审查?
PMP认证培训怎么选机构?
PMP培训机构是什么?
PMP认证考试需要准备什么?
北京PMP考试地点在哪里?
上海PMP考试地点在哪里?
广州PMP考试地点在哪里?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库