以下城市均已开通:
关闭
当前位置:PMP团购网 > PMP考试资料 > 正文

PMP考试每天一练-2018年PMP考试试题131

作/转载者:PMP团购网      发布时间:2018/10/31        点击: 208

PMP考试试题一:

Due to a failure in prompt reporting, a project manager discovers that a project is behind schedule and over budget. What should the project manager prepare to prevent this in the future?

A.Change management plan

B.Communication model analysis

C.Communications management plan

D.Stakeholder analysis

项目经理最近发现他管理的项目出现进度滞后,费用超出预算等问题。但是没有人及时汇报这些情况。项目经理做好下面哪一项工作就可以避免类似问题?

A.变更管理计划

B.沟通模型分析

C.沟通管理计划

D.干系人分析

PMP答案解析:本题选项见沟通管理计划内容,将干系人需要的内容,形式,频率,格式等内容进行明确共识并记录,项目经理也是项目干系人

PMP参考答案:C

PMP考试试题二

During the project’s execution phase, a key executive reports that a portion of the project will be given to a new external vendor for development. The new vendor provides their additional requirements which cause a potential delay in the delivery schedule.What should the project manager do next?

A.Notify stakeholders of the scope change according to the communications management plan

B.Update the risk management plan

C.Adjust the project management plan, schedule, and priorities to control the impact

D.Conduct a risk reassessment

在项目执行阶段,一名关键主管报告将把项目的一部分外包给一名新的外部供应商开发。这名新供应商提供了他们的额外需求,导致交付进度可能发生延迟。项目经理下一步该怎么做?

A.按照沟通管理计划通知干系人范围变更

B.更新风险管理计划

C.调整项目管理计划、进度和优先级控制的影响

D.执行风险再评估

PMP答案解析:导致交付进度“可能”发生延迟,说明是风险

PMP参考答案:D

阅读本文的人还阅读了:
PMP考试有题库吗?
PMP考试报名费是多少?
PMP考试时间一年有几次?
PMP考试三个月来得及吗?
广州PMP考试地点
PMP考试报名资格怎么审查?
上海PMP考试地点在哪里?
广州PMP考试地点在哪里?

留言讨论区
我也来说两句


获取更新

合作与联系

友情链接: PMP培训团购网 项目管理者联盟 电商第一站 pmp百科 磨石建筑教育 SPC培训 企业管理培训 清晖PMP培训 光环国际 网站建设 青岛旅行社
PMP团购导航
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
东北PMP团购
其他城市团购
远程PMP团购
PMP团购网
免费领PMP团购券