PMP考试每天一练-2018年PMP考试试题127

转载者:PMP团购网      发布时间:2018/10/22        点击: 1838

PMP考试试题一:

During project implementation, the project management notices a high amount of rework. The project manager should consult which of the following for strategies to decrease the amount of rework

A.Process improvement plan

B.Quality metrics

C.Scope statement

D.Quality management plan

在项目实施期间,项目经理注意到返工量很大。项目经理应查阅下列哪一项?

A.过程改进计划

B.质量测量指标

C.范围说明书

D.质量管理计划

PMP答案解析:PMBOK原话:应该在项目早期就对质量管理计划进行评审,以确保决策是基于准确信息的。这样做的好处是,更加关注项目的价值定位,降低因返工而造成的成本超支金额和进度延误次数。

PMP参考答案:D

PMP考试试题二

The project management office asks the project manager to formally close the project. The project manager ensures the final product is formally delivered, accepted, and the project documents are updated.The project manager should do which of the following?

A.Release all of the resources

B.Audit quality control

C.Perform quality assurance

D.Edit the risk response register

项目管理办公室要求项目经理正式收尾项目。项目经理确保最终产品正式交付、验收及项目文件均已更新。项目经理应该采取下列哪一项措施?

A.解散所有资源

B.审计质量控制

C.实施质量保证

D.编辑风险应对登记册

PMP答案解析:最终产品已经移交、文件均已归档,根据收尾流程接下来应该释放资源

PMP参考答案:A

阅读本文的人还阅读了:
PMP证书在哪个行业比较有用
PMP的价值在哪?
PMP认证考试的报名条件?
PMP是什么?
长春PMP考试地点在哪里?
哈尔滨PMP考试地点在哪里?
重庆PMP考试地点在哪里?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库