PMP考试每天一练-2018年PMP考试试题126

转载者:PMP团购网      发布时间:2018/10/19        点击: 2531

PMP考试试题一:

A contract for a company’s software solution is awarded to a vendor. After implementation the company’s users find issues that the company’s support team must address. Key clauses in the support agreement, which were included in the procurement contract, are unclear and biased towards the vendor.On which of the following processes should the project manager have focused to avoid the conflict?

A.Plan procurement management

B.Conduct procurements

C.Manage procurements

D.Contract procurements

一家公司的软件解决方案合同授于卖方。实施之后,该公司的用户发现了一些该公司支持团队必须 解决的问题。包含在采购合同中的支持协议关键条款不明确,全偏向于卖方。
项目经理应关注下列哪一个过程来避免这项冲突?

A. 制定采购管理计划

B. 实施采购

C. 管理采购

D. 控制采购

PMP答案解析:On which of the following processes should the project manager have focused to avoid the conflict?题目问的是本应该关注哪个过程组。 PM本应该关注实施采购过程,合同的正式授予。

PMP参考答案:B

PMP考试试题二

A team is not able to follow the project specifications. However, there is no formal report of this issue. As a result, the project manager cannot confirm that the team is technical competence to perform the work.What should the project manager do next?

A.Request a quality audit review by the quality assurance team

B.Perform the control quality process

C.Review the situation with the project’s sponsor

D.Ask the team members about their technical issues in meeting the project requirements

团队不能遵循项目技术规范。但是,没有这个问题的正式报告。结果,项目经理无法确认团队是否有执行工作的技术能力项目经理接下来应该怎么做?

A.申请由质量保证团队进行质量审计审查

B.执行质量控制流程

C.与项目发起人审查这种情况

D.询问团队成员有关他们满足项目要求的技术问题

PMP答案解析:题干说团队不能遵循项目技术规范, PM接下来应该执行质量审计。质量审计是用来确定项目活动是否遵循了组织和项目的政策、过程与程序

PMP参考答案:A

阅读本文的人还阅读了:
PMP是什么?
PMP考试有什么科目?
PMP考试三个月来得及吗?
广州PMP考试地点
PMP考试报名资格怎么审查?
PMP认证培训怎么选机构?
潍坊PMP考试地点在哪里?
长春PMP考试地点在哪里?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库