PMP考试试题一:

During a project's closure phase, the project manager creates a project summary and review in which team members share lessons learned, what tool or technique is the project manager using?

A.Summary reports

B.Expert judgment

C.Analytical techniques

D.Meetings

在项目收尾阶段,项目经理和他的团队进行了项目总结和检讨,其中包含团队成员各自在项目中的收获和成功分享。他采用了哪种工具?

A汇总报告

B.专家判断

C.分析技术

D.会议

PMP答案解析:结束项目或阶段,通过会议进行经验教训的总结等

PMP参考答案:D

PMP考试试题二

The project management plan is distributed to all key stakeholders. However, the project sponsor and the customer have comments and want to make some changes.Who should receive this feedback and take the appropriate actions

A.Change control board

B.Project sponsor

C.Project manager

D.Project team

已将项目管理计划分发给所有关键干系人。然而,项目发起人和客户有意见,并希望做一些改进。谁应负责收取该反馈并采取适当的行动?

A.变更控制委员会

B.项目发起人

C.项目经理

D.项目团队

PMP答案解析:实施整体变更控制过程贯穿项目始终,项目经理对此负最终责任

PMP参考答案:C

阅读本文的人还阅读了:
PMP考试报名资格怎么审查?
PMP认证培训怎么选机构?
PMP培训机构是什么?
PMP认证考试需要准备什么?
潍坊PMP考试地点在哪里?
长春PMP考试地点在哪里?
哈尔滨PMP考试地点在哪里?
重庆PMP考试地点在哪里?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库