PMP考试每天一练-2018年PMP考试试题103

转载者:PMP团购网      发布时间:2018/8/31        点击: 2259

PMP考试试题一:

Due to technical issues, a project is stopped in the early stages. When closing the project, what should the project manager do?

A.Update and archive the work breakdown structure

B.Update and archive the project charter

C.Document and archive the lessons learned

D.Inform the technical supervision about the issues

因为技术问题,项目在早期阶段停止了,项目收尾时,项目经理应该怎么做?

A.更新并存档工作分解结构

B.更新并存档项目章程

C.记录并存档经验教训

D.将相关问题通知技术主管

PMP答案解析:项目收尾时要记录并总结经验教训

PMP参考答案:C

PMP考试试题二

During a project meeting, a team member identifies and submits a risk to the project manager. After an evaluation of the risk, the project team determines the impact, probability, and a risk response.Before performing these activities, what process must be completed?

A. Plan Risk Management

B. Identify Risks

C. Perform Quantitative Risk Analysis

D. Plan Risk Responses

在项目会议上,一名团队成员识别到一个风险,并将其提交给项目经理。在评估完风险后,项目团队确定了影响、发生概率和风险应对措施。执行这些活动之前,必须完成哪个过程?

A. 制定风险管理计划

B. 识别风险

C. 实施定量风险分析

D. 制定风险应对计划

PMP答案解析:在识别风险、风险分析、规划风险应对之前,要做的是规划风险管理

PMP参考答案:A

阅读本文的人还阅读了:
PMP考试内容是什么?
PMP考试有题库吗?
PMP考试报名费是多少?
PMP考试时间一年有几次?
PMP考试时间具体是什么?
杭州PMP考试地点在哪里?
苏州PMP考试地点在哪里?
无锡PMP考试地点在哪里?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库