PMP考试试题一:

During a weekly project stakeholder meeting, a Product support manager brings up a concern that is important to customer satisfaction, but may require some product design changes. What should the project manager do next?

A.Record the concern in the issue log.

B.Update the project management plan.

C.Update the risk register.

D.Create a change request.

在项目进度周会上,一位产品支持经理表达了一项对于客户满意度很重要的担忧,但是这将需要进行一些产品设计变更,PM接下来应当怎么做。

A.将这种担忧记录在问题日志中

B.更新项目管理计划

C.更新风险登记册

D.发起一项变更请求

PMP答案解析:客户表达的是一种担忧,可认为是风险,应该更新进风险登记册中

PMP参考答案:C

PMP考试试题二

A storm damages a data center, causing a delay to the project. as a result of this unexpected event, what should the project manager do next?

A.Use management reserve funds to generate a workaround

B.Delay the project and wait for management’s directions

C.Update the schedule and advise the project sponsor

D.Meet with the project team to discuss the immediate response

一场风暴损坏了数据中心,导致项目延迟。由于这是一个意外事件,项目经理下一步该怎么做?

A.使用管理储备金来生成一个权变措施

B.延迟项目,并且等待管理层的只是

C.更新进度,并且通知项目发起人

D.与项目团队开会讨论直接的应对措施

PMP答案解析:未知风险发生,采用权变措施、动用管理储备

PMP参考答案:A

阅读本文的人还阅读了:
PMP认证考试需要准备什么?
PMP报名时间是哪天?
PMP考点在哪里?
PMP认证费用多少?
PMP认证多少钱?
青岛PMP考试地点在哪里?
潍坊PMP考试地点在哪里?
长春PMP考试地点在哪里?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库