PMP考试每天一练-2020年PMP考试试题16

转载者:PMP团购网      发布时间:2020/1/31        点击: 1552

PMP考试试题一:

As the project experiences process failures, which method should the project manager use to identify where the concerns exist and opportunities for improvement?

A.Run charting

B.Affinity diagramming

C.Flowcharting

D.brainstorming

因为项目经历过程失败,项目经理应使用哪种方法来确定存在的问题以及改进机会?

A.趋势图

B.亲和图

C.流程图

D.头脑风暴法

PMP答案解析:流程图也叫过程图,过程失败需要使用过程图来分析哪个环节出错了。

PMP参考答案:C

PMP考试试题二

During a project's concept, prototype, development, and testing phases, additional funding is requested several times. After the product launch, the budget is updated and the project manager determines there is a negative cost variance (CV).Which of the following does this indicate?

A. Original budget is greater than the total cost at completion

B. Total cost of the project is greater than the planned value (PV)

C. Total incremental funding exceeded the original budget

D. Earned value (EV) is greater than the actual cost (AC)

在项目的概念、原型、开发和测试阶段,多次请求提供额外资金。在发布产品后更新预算,项目经理确定成本偏差(CY)为负的。这表明了下列哪一项?

A.原始预算大于完工时总项目成本

B.项目总成本大于计划价值(PV)

C.总增量资金超出原始预算

D.净值(EV)大于实际成本(AC)

PMP答案解析:CV<0说明成本超支,项目总成本大于计划价值。

PMP参考答案:B

阅读本文的人还阅读了:
PMP考试难度?
PMP考试骗局?
PMP考试报名官网是什么?
PMP考试科目是什么?
pmp考试教材?
PMP考试含金量?


网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库