PMP考试每天一练-2020年PMP考试试题9
PMP考试试题一: At the last minute, a project team implements a new feature that is not included in the scope statement. To obtain customer approval, what process should the project manager implement next? A. Plan Scope Management B. Validate Scope C. Perform Integrated Change Control D. Perform Qualitative Risk Analysis 在最后一刻,项团队实施了范围说明书中未包含的新功能。若要获得客户的批准,项目经理下一步应执行哪个过程? A.制定范围管理计划 B.核实范围 C.执行整体变更控制 D.执行定性风险分析 PMP答案解析:未包含的新功能要获得客户的批准,首先应该进行变更,把新功能添加到范围基准中。 PMP参考答案:C PMP考试试题二 In the project planning period, should use what technology to digital quantification risk on overall project objectives impact? A. Develop risk response plan B. Risk identification C. Quantitative risk analysis D. Qualitative risk analysis 在项目规划期间,应使用什么技术来数字量化确定风险对总体项目目标的影响? A. 制定风险响应计划 B. 识别风险 C. 定量风险分析 D. 定性风险分析 PMP答案解析:通过定量分析来评估对项目总体目标的影响。 PMP参考答案:C |