PMP考试每天一练-2020年PMP考试试题6
PMP考试试题一: A client had requested that three new features be added to a project and approved the subsequent change request. What should be done next? A. Consult all project stakeholders in the stakeholder register to confirm agreement. B. Implement the changes. C. Revise the project charter. D. Ensure all project team members approve the changes. 客户请求对项目添加三个新功能,并批准后续的变更请求。下一步应该怎么做? A.咨询干系人登记册中的所有项目干系人,确认获得一致意见。 B.实施变更。 C.修订项目章程。 D.确保所有项目团队成员批准变更。 PMP答案解析:根据题意,四个选项中最好的选项为B,变更被批准后,可以实施变更。 PMP参考答案:B PMP考试试题二 The sponsor asks the project manager to quickly implement the primary deliverables* The project manager attempts to allocateresources to the first tasks, but realizes resources are not available.To identify the required skills, which of the following documents should the project manager reference first. A. Resource calendars B. Project scope statement C. Human resource management plan D, WBS dictionary 项目发起人要求项目经理快速实施主要可交付成果。项目经理尝试将资源分配给第一个任务,但意识到资源不可用。为识别所需技能,项目经理应首先参考下列哪一份文件? A.资源日历 B.项目范围说明书 C.人力资源管理计划 D.WBS字典 PMP答案解析:估算活动资源的输入,资源日历,包括资源可用性、资源类型和资源性质。 PMP参考答案:A |