PMP考试每天一练-2019年PMP考试试题52
PMP考试试题一: A project implementing a new learning system is created which is also a strategic priority of the chief information officer (CIO). However, the company announces the CIO’s departure and names the new CIO.After meeting with the team. What should the project manager do next? A.advise the new CIO of the importance of the learning system B.suspend the project until the new CIO’s goals are established C.update the risk register, execute the risk response, and document the results D.analyze enterprise environmental factors, review the project charter, and proceed with the project 一个实施新学习系统的项目被创建,该项目也是首席执行官(CIO)的战略优先级。但是,公司宣布该CIO离职,并任命新的CIO。与团队开会之后,项目经理下一步该怎么做? A.告知新的CIO这个学习系统的重要性。 B.中止该项目,直至新CIO的目标确立。 C.更新风险登记册,执行风险并记录结果。 D.分析事业环境因素,审查项目章程并继续该项目。 PMP答案解析:了解新的COI是否愿意继续这个项目、了解这个项目是否符合公司战略,再审查项目章程看看是否保持一致,如果一致则可以继续项目 PMP参考答案:D PMP考试试题二 A company is working on project A. In two weeks, the company will start project B. To build a team for project B, the project manager requests resources from project A.To verify resource availability, what document should project s project manager review? A. Project staff assignments B. Human resource management plan C. Project schedule D. Staff release plan 一家公司正在从事项目A.两周内,该公司将开始项目B.为了给项目B创建一支团队,项目经理请求提供项目A的资源。若要确认资源可用性,项目A的项目经理应审查哪一份文件? A.项目人员配备 B.人力资源管理计划 C.项目进度计划 D.人员解散计划 PMP答案解析:人力资源管理计划提供了关于如何定义、配备、管理及最终遣散项目人力资源的指南 PMP参考答案:B |