PMP考试试题一:

After identifying a potential risk that could delay the project, the project manager implements the planned response. What should the project manager do next?

A.Update the project management plan

B.Request approval to use contingency reserves

C.Compress the project schedule

D.Perform a risk analysis

在识别可能延迟项目的潜在风险后,项目经理实施了规划的应对措施。项目经理接下来应该怎么做?

A.更新项目管理计划

B.请求批准使用应急储备

C.压缩项目进度

D.执行风险分析

PMP答案解析:控制风险过程的输出:项目管理计划更新。应急储备PM可以直接使用,不需要被批准,排除B

PMP参考答案:A

PMP考试试题二

A project manager is assigned to a company’s technology project. A competitor is delivering the same product to market using a different technology. As a result, the company’s project sponsor determines there is on longer a need for the project.What should the company’s project manager do next?

A. Release the project team

B. Terminals the project

C. Update the project management plan

D. Discuss the possibility of continuing the project with the project sponsor

项目经理被任命管理公司的一个技术项目。竞争对手正在使用不同的技术向市场投放相同的产品。结果,公司的项目发起人决定该项目不再有存在的必要性。该公司的项目经理下一步该怎么做?

A.解散项目团队

B.终止项目

C.更新项目管理计划

D.项目发起人讨论继续项目的可能性。

PMP答案解析:发起人已经决定项目没有存在的必要性,PM下一步应该进行项目收尾

PMP参考答案:B

阅读本文的人还阅读了:
2019年PMP考试时间是什么?
2019年PMP考试费用是多少?
2019年PMP报考条件是什么?
PMP百科网站
工作年限不够可以考PMP吗?
PMP证书在哪个行业比较有用
杭州PMP考试地点在哪里?
苏州PMP考试地点在哪里?
无锡PMP考试地点在哪里?
常州PMP考试地点在哪里?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库