以下城市均已开通:
关闭
当前位置:PMP团购网 > PMP考试资料 > 正文

PMP考试每天一练-2018年PMP考试试题135

转载者:PMP团购网      发布时间:2018/11/7        点击: 2184

PMP考试试题一:

A customer agrees to a two-hour interruption dung the launch of a data center migration project Due to some external factors, the interruption exceeds the agreed-upon two-hour timeframe. What should the project manager do?

A.Update the risk management plan and communicate it to the project stakeholders.

B.ASK the team to create a workaround, and submit a change request to extend the schedule.

C.Schedule a meeting to determine the root cause.

D.Inform the customer, and schedule a meeting to create a workaround.

客户同意在开展数据中心迁移项目期间中断两小时。但由于一些外部因素,中断时间超出约定的两小时时间范围。项目经理应该怎么做?

A.更新风险管理计划,并与项目干系人沟通。

B.要求团队创建权变措施,并提交变更请求延长进度计划。

C.安排一次会议,确定根本原因。

D.安排一次会议创建权变措施

PMP答案解析:推荐D参考答案,是否需要B参考答案中的权变措施后面的内容,需要根据权变措施的内容来决定,而不是同步做出决定

PMP参考答案:D

PMP考试试题二

While working with a customer to validate a deliverable, the customer notifies the project manager that several required data fields are missing. The customer indicates that the data fields are included in the requirements.During which of the following processes should the project team have discovered this error?

A.Identify benchmark

B.Report performance

C.Control scope

D.Control quality

当与客户合作核实可交付成果时,客户通知项目经理多项必须的数据字段趋势。客户表示这些数据字段已包含在需求当中。项目团队应该在以下哪一个过程中发现这个错误?

A.识别标杆

B.报告绩效

C.控制范围

D.控制质量

PMP答案解析:需求没有被正确执行,导致客户验收时出现问题。问题本应该在控制范围时就发现

PMP参考答案:C

阅读本文的人还阅读了:
PMP考试有什么科目?
PMP考试三个月来得及吗?
广州PMP考试地点
PMP考试报名资格怎么审查?
PMP认证培训怎么选机构?
青岛PMP考试地点在哪里?
潍坊PMP考试地点在哪里?
长春PMP考试地点在哪里?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库