PMP考试每天一练-2018年PMP考试试题93
PMP考试试题一: The project manager wants to consider developing the project internally or outsourcing the work to a third-party contractor. Which of the following should the project manager do next? A.Cost-benefit analysis B.Make-or-buy analysis C.SWOT analysis D.Vendor bid analysis 项目经理希望考虑内部开发项目还是将工作外包给第三方承包商。项目经理接下来应执行下列哪一项? A.成本效益分析 B.自制或外购分析 C.SWOT分析 D.卖方投标分析 PMP答案解析:考虑内部开发还是将工作外包给第三方承包商,自制或外购分析 PMP参考答案:B PMP考试试题二 During a project’s planning phase, the project manager of project A learns that specific equipment is required for an activity. It is the project manager of project B’s responsibility to acquire and install this equipment.What type of dependency reflects the relationship between the activity and the required equipment? A.Discretionary internal B.Discretionary external C.Mandatory internal D.Mandatory external 在项目规划阶段,项目A的项目经理了解到某项活动需要使用特殊设备。而采购安装该设备是项目B项目经理的责任。哪一种依赖关系类型反映了这项活动与所需设备之间的关系? A.选择性内部依赖关系 B.选择性外部依赖关系 C.强制性内部依赖关系 D.强制性外部依赖关系 PMP答案解析:项目A依赖于这项特殊设备,因此是强制性。而这项设备是另一个项目B采购的,所以是外部关系 PMP参考答案:D |