PMP考试每天一练--2016年PMP考试试题及答案解析8
8、Verify Scope the process of obtaining stakeholder's formal acceptance of the completed project scope and associated deliverables.In this context,which statement related to Verify Scope correct? A.Verify Scope similar to Quality Control. B.Quality Control is generally pertormed before Scope Verification,but these two processes may also be done in parallel. C.Verify Scopeindicates the end of a project. D.Verify Scope the final sign-off from the sponsor and customer. 8、核实范围是个过程用来获得项目干系人对项目已完成范围和成果的正式接受。下列关于核实范围说法中正确的是? A、核实范围和质量控制相似 B、质量控制通常在核实范围之前进行,两个过程也可以同时进行 C、核实范围意味着项目的结束 D、核实范围是从出资人或客户那里得到最终的签字 正确答案:B 试题解答:核实范围和质量控制不同;核实范围是成果得到客户或干系人认可的过程,不代表项目结束。参考:PMBOK2008 P123。 |