PMP考试每天一练-2020年PMP考试试题79
PMP考试试题一: A company will be restructuring within the next few months. The project manager meets with the newly formed project team to assess the risk to their project.What technique could the project manager use to identify high-level risks? A.Decision tree B.PERT chart C.SWOT analysis D.Earned value analysis 一家公司将在接下来的数月内重组。项目经理与新成立的项目团队开会,评估项目的风险。项目经理可以使用什么技术来识别高风险? A.决策树分析 B.PERT图 C.SWOT分析 D.挣值分析 PMP答案解析:识别风险的工具: SWOT分析。 PMP参考答案:C PMP考试试题二 A customer needs assurance that the project team has a clear plan for delivering a satisfactory. quality product. Which of the following documents should the project manager provide to the customer? A. Project charter B. Scope management plan C. Quality management plan D. Quality metrics 一家客户需要项目团队保证拥有明确的计划,交付令人满意的高质量产品。项目经理应该向客户提供下列哪一项? A.项目章程 B.范围管理计划 C.质量管理计划 D.质量测量指标 PMP答案解析:质量管理计划:描述将如何实施组织的质量政策,以及项目管理团队准备如何达到项目的质量要求。 PMP参考答案:C |