以下城市均已开通:
关闭
当前位置:PMP团购网 > PMP考试资料 > 正文

PMP考试每天一练-2020年PMP考试试题57

转载者:PMP团购网      发布时间:2020/4/29        点击: 2491

PMP考试试题一:

During a meeting, the project manager notices that a key project team member tacks the knowledge and skills required to complete tasks on the critical path. This could cause a delay to the project’s end date and impact stakeholder satisfaction.To reduce this risk, what should the project manager do next?

在一次会议上,项目经理注意到一名关键项目团队成员缺乏完成关键路径上任务所需的知识和技能。这会导致延迟项目结束日期,并影响干系人的满意度。为降低这个风险,项目经理下一步该怎么做?

A.接受风险,避免增加成本

B.将这些具体任务承包给一名专家

C.向该团队成员提供培训

D.修订进度计划,考虑资源的技能水平

PMP答案解析:选项C是减轻。 选项A是风险接受。 选项B是风险转移。 选项D是风险回避。

PMP参考答案:C

PMP考试试题二

A project team reports that the peer review process has non-valued activities. The quality team must review the observations and process the overall adherence. Which of the following does the quality team perform?

A. Quality adherence

B. Quality audit

C. Quality control

D. Quality assurance

项目团队报告同行评审过程存在无价值的活动。质量团队必须审查观察结果并处理整体一致性。质量团队执行的是下列哪一项?

A.质量一致性

B.质量审计

C.质量控制

D.质量保证

PMP答案解析:过程分析检查在过程运行期间遇到的问题、制约因素,以及发现的非增值活动。

PMP参考答案:D

阅读本文的人还阅读了:
昆山PMP考试地点在哪里?
南昌PMP考试地点在哪里?
廊坊PMP考试地点在哪里?
PMP证书含金量大吗?
PMP证书可以挂靠吗?
武汉PMP考试地点在哪里?
长沙PMP考试地点在哪里?
烟台PMP考试地点在哪里?
济南PMP考试地点在哪里?

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库