PMP考试每天一练-2019年PMP考试试题96
PMP考试试题一: To officially close a project, what should the project manager do? A. Close out the risk register. B. Validate scope. C. Update the project management plan. D. Close out procurements. 正式收尾项目时,项目经理应该怎么做? A.关闭风险登记册。 B.核实范围。 C.更新项目管理计划。 D.结束采购工作。 PMP答案解析:四个选项中 D选项属于项目收尾过程组的工作。 PMP参考答案:D PMP考试试题二 To improve its products and ensure customer satisfaction, a company implements a quality process that places emphasis on the statistical measurement of the prouct. What is the company implementing? A. training B. total quality management (TQM) C. scrap rather than rework D. improved inspection 为了改进其产品,确保客户的满意度,一家公司实施了质量过程,将重点放在产品的统计测 公司正在实施哪一项? A.培训 B.全面质量管理(TQM) C.废料而不返工 D.改进检查 PMP答案解析:以客户为导向,以质量为重点进行持续改进。 PMP参考答案:B |