PMP考试每天一练-2019年PMP考试试题90
PMP考试试题一: Customer a implements a new system and awards the implementation phase to an external supplier B. A contract is signed with external supplier B. Supplier B would describe the contract as which of the following? A.Input to developing the project charter B.Output from developing the project charter C.Input to developing the project management plan D.Input to developing the schedule 客户A实施一个新系统,并将实施阶段授予外部供应商B来执行,并与供应商B签订合同。供应商B将会将该合同描述为下列哪一项? A.制定项目章程的输入 B.制定项目章程的输出 C.制定项目管理计划的输入 D.制定进度计划的输入 PMP答案解析:合同、协议是制定项目章程的输入。 PMP参考答案:A PMP考试试题二 A critical project component is delivered by an external contractor and is evaluated for compliance with established technical requirements. What process is being performed? A. Plan Quality Performance B. Control Quality C. Assess Quality Risk D. Perform Quality Assurance 一个关键项目组件是由外部承包商交付的,并评估是否符合既定的技术要求。这正在执行哪个过程? A.制定质量绩效计划 B.控制质量 C.评估质量风险 D.实施质量保证 PMP答案解析:评估产品是否符合要求,是控制质量。 PMP参考答案:B |