PMP考试每天一练-2019年PMP考试试题78
PMP考试试题一: The project team must make a buy-versus-build decision on a critical piece of equipment. Multiple stakeholders offer suggestions, however, the project manager wants to retain final control of the decision.What is the project manager’s decision-making style() A.Collaborative B.Command C.Consultative D.consensus 项目团队必须对一个关键设备做出自制或外购决策。多名项目干系人都提供了建议,但是项目经理希望保留决策的最终控制权。项目经理的决策方式属于哪一种? A.协作 B.命令 C.咨询 D.协商 PMP答案解析:项目经理常用的4 种决策方式是:命令、咨询、协商和抛硬币(随机)。咨询:其他人出主意,PM做决定。 PMP参考答案:C PMP考试试题二 To improve manufacturing performance, a project manager designs a plan to prevent unnecessary scrap, waste, and rework. If successful, what outcome should be expected? A. Reduced resource requirements B. Increased cost performance C. Lowered cost of quality (COQ) D. Improved customer satisfaction 为了提高制造绩效,项目经理设计了一个计划,以避免产生不必要的废料、浪费和返工。如果成功的话,应该可以预期会出现什么结果 A.降低资源需求 B.提高成本绩效 C.降低质量成本(COQ) D.提高客户满意度 PMP答案解析:废料、浪费和返工都属于质量成本中的非一致性成本 PMP参考答案:C |