当前位置:PMP团购网 > PMP考试资料 > 正文

PMP考试每天一练-2019年PMP考试试题77

转载者:PMP团购网      发布时间:2019/6/28        点击: 1861

PMP考试试题一:

A project manager is required to complete a project in three months, which allows insufficient time for selecting the optimum supplier. The project manager selects a supplier with whom they have worked before and signs a contract. What is the risk in this situation?

A. Lack of a legally binding agreement

B. Lack of proper scope definition

C. Ability of the supplier to deliver the goods

D. Collusion between the supplier and the project manager

项目经理需要在三个月内完成一个项目,这使得没有足够的时间选择最佳的供应商。项目经理选择了与他们以前合作过的供应商并签订合同。这种情况的风险是什么?

A.缺乏具有法律约束力的协议

B.缺乏适当的范围定义

C.供应商交付货物的能力

D.供应商和项目经理之间相互勾结

PMP答案解析:本题意表明采用了单一来源供应商,会有交付风险

解析:C

PMP参考答案:

PMP考试试题二

A new team member with no practical project experience is assigned to an ongoing project. The project manager assigns a difficult task to the new team member.What action should the project manager now take?

A. Assign a mentor for the new team member and closely monitor their progress

B. Recommend that the new member undertake a self-study training program

C. Allow the new team member to work alone, but report daily to the project manager.

D. Provide the new team member with the project management plan and assign a contact person.

一名没有实际项目经验的新团队成员被分配到一个正在进行当中的项目。项目经理向该团队成员分配了一项困难任务。项目经理现在应该采取什么措施?

A.为该新团队成员分配一位指导者,并密切监测他们的进展情况。

B.建议该新团队成员参加自学培训课程。

C.允许该新团队成员单独工作,但应每日向项目经理报告工作。

D.向该新团队成员提供项目管理计划,并指定—名联系人。

PMP答案解析:没有经验的团队成员要执行一项困难任务,可以通过培训、指导来提高技术技能。

PMP参考答案:A

阅读本文的人还阅读了:
PMP认证考试的报名条件?
PMP是什么?
PMP考试有什么科目?
PMP考试内容是什么?
PMP考试有题库吗?
PMP考试报名费是多少?
PMP考试时间一年有几次?
PMP考试时间具体是什么?
PMP考试报名时间是什么?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库