PMP考试每天一练-2019年PMP考试试题70

转载者:PMP团购网      发布时间:2019/6/12        点击: 1686

PMP考试试题一:

During a project's testing phase ,several issues are identified; however, the solutions appear to conflict with other technology solutions already in place. The project management office (PMO) is asked to review the project's life cycle, determine what went wrong, and recommend corrective actions. After completing the assessment, the PMO identifies several inconsistencies with the processes. What should the PMO recommend?

A.Project audits and status checks

B. More stringent project selection criteria

C.Project stage gate reviews

D. Systems and design reviews

在项目的测试阶段,已识别多个问题:但是,解决方案似乎与其他已经存在的技术解决方案冲突,项目管理办公室(PMO)被要求审查该项目的生命周期,确定什么地方出了错,并提出纠正措施,完成评估后,项目管理办公室识别出过程的一些不一致之处。项目管理办公室应建议哪一项?

A.项目审计和状态检查

B.更严格的项目选择标准

C.项目阶段关口审查

D.系统和设计评审

PMP答案解析:项目的每个阶段结束要做阶段审查

PMP参考答案:C

PMP考试试题二

Before the bid or proposal submittals, a company meets with all prospective sellers. The company wants to ensure that all prospective sellers have a clear and common understanding on the procurement process.The company is in which of the following procurement management processes?

A.Conduct procurements

B.Plan procurements

C.Control procurements

D.Close procurements

提交标书或建议书之前,一家公司与所有潜在卖方开会。公司希望确保所有潜在卖方对采购流程有一个明确的共识。该公司正处于下列哪一项采购管理过程组中?

A.实施采购

B.计划采购

C.控制采购

D.结束采购

PMP答案解析:召开投标人会议是实施采购的工具

PMP参考答案:A

阅读本文的人还阅读了:
PMP报名时间是哪天?
PMP考点在哪里?
PMP认证费用多少?
珠海PMP考试地点在哪里?
东莞PMP考试地点在哪里?
保定PMP考试地点在哪里?
杭州PMP考试地点在哪里?
苏州PMP考试地点在哪里?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库