PMP考试试题一:

A project manager in a functional organization assigns a resource to an activity. The resource is committed at 100 percent utilization and the schedule performance index (SPI) for that activity is 0.79.What should the project manager do next?

A. Recalculate the schedule based on the resource's performance.

B. Identify corrective actions with the line manager.

C. Reward the resource for an excellent performance.

D, Update the progress report based on actual progress.

处于职能型组织的项目经理为一项活动分配了一名资源。该资源全身心为项目工作,而该项活动的进度绩效指数(SPI)为0.79。项目经理下一步应该怎么做?

A.根据资源的绩效重新计算进度。

B.与直线经理一起确定纠正措施。

C.因为其优异的绩效表现奖励该资源。

D.根据实际进展情况更新进度报告。

PMP答案解析:推荐答案为B,题干重点应当是放在资源管理权利上,职能型组织中资源的管理权利属于职能经理,出现问题,需要与职能经理一起协商解决

PMP参考答案:B

PMP考试试题二

A project manager completes a large project that requires equipment purchases from a local vendor. Which of the following activities would occur in the close procurements process?

A.Updating the procurement management plan

B.Updating the terms and conditions of the contract

C.Archiving the contract documentation

D.Archiving the project management plan

项目经理完成了一个需要从当地供应商采购设备的大型项目。下列哪一项活动将发生在结束采购过程中?

A.更新采购管理计划

B.更新合同条款和条件

C.合同文档存档

D.项目管理计划存档

PMP答案解析:结束采购的输出:组织过程资产更新

PMP参考答案:C

阅读本文的人还阅读了:
广州PMP考试地点
PMP考试报名资格怎么审查?
PMP认证培训怎么选机构?
PMP培训机构是什么?
PMP考试时间一年有几次?
PMP考试时间具体是什么?
PMP考试报名时间是什么?

留言讨论区
我也来说两句


获取更新

合作与联系

友情链接: PMP培训团购网 安徽成考网 健身教练培训 项目管理者联盟 天津坦途教育网 磨石建筑教育 SPC培训 光环国际 青岛旅行社 湖南自考
PMP团购导航
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
东北PMP团购
其他城市团购
远程PMP团购
PMP团购网
免费领PMP团购券