PMP考试每天一练-2019年PMP考试试题38

转载者:PMP团购网      发布时间:2019/4/8        点击: 2241

PMP考试试题一:

A company decides to launch a new project to increase its revenues. A project manager is selected this new project.In which of the following documents will the high-level requirements and stakeholders expectations be found?

A.project management plan

B.project charter

C.stakeholder register

D.activities list

公司决定推出一项新产品来增加公司收入。项目经理被选择来管理这个新项目。下列哪一份文件中可以找到高层次需求和干系人期望?

A.项目管理计划

B.项目章程

C.干系人登记册

D.活动清单

PMP答案解析:章程中包含高层次需求和干系人期望

PMP参考答案:B

PMP考试试题二

A project team plans a meeting with business supervisors from various departments to discuss the requirements of a business system to be developed, The project manager appoints a new team member to conduct the meeting. On the first day, the supervisors attending the meeting express conflicting opinions due to the different business characteristics and processes, what should the project manager do?

A.Ask the company's senior leadership to appoint an attendee as the moderator for day two.

B.Conduct anonymous polling of the attendees on each discussion point to gain consensus.

C.Appoint an experienced team member to moderate day two.

D.Appoint members of the project team to follow up with the business suspensors on day two.

某项目组召集公司各区域业务主管召开两天的会议,讨论准备开发的业务系统的要求。项目经理委派了一位新同事负责主持该次会议。第一天会上,参会的各区域业务主管们由于业务属性与流程不同而意见相左,在若干问题上都没有达成共识。项目经理了解该情况后该怎么做?

A.要求公司上级领导在与会人员中任命一位总负责以控制第二天会议进程。

B.对每个讨论命题进行无记名投票表决,少数服从多数。

C.安排一位受过训练的同事主持第二天的会议。

D.第二天安排更多项目组成员分别和各区域业务主管进行跟进。

PMP答案解析:题干强调“在若干问题上都没有达成共识”,因此重点是需要群体决策,相对多数原则

PMP参考答案:B

阅读本文的人还阅读了:
pmp认证培训费用多少?
pmp项目管理师是什么?
pmp证书是什么?
PMP证书有用吗?
PMP认证考试需要准备什么?
PMP报名时间是哪天?
PMP考点在哪里?
PMP认证费用多少?
PMP认证多少钱?

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库