PMP考试每天一练-2019年PMP考试试题33

作/转载者:PMP团购网      发布时间:2019/3/29        点击: 460

PMP考试试题一:

A construction project requires the procurement of various materials. In a complex procurement process, what input should assist the project manager with proposal evaluation?

A.Expert judgment

B.Source selection criteria

C.Independent estimates

D.Requirements documentation

一个施工项目需要采购各种材料。在复杂的采购过程中,哪一项输入有助于项目经理进行建议书评估?

A.专家判断

B.供方选择标准

C.独立估算

D.需求文档

PMP答案解析:供方选择标准的规划采购的输出,是采购文件的一部分,作为依据对卖方建议书进行评级和打分

PMP参考答案:B

PMP考试试题二

While developing a project charter for an internal project, the project manager realizes some functional managers’ expectations conflict with each other and could negatively impact the project.What should the project manager do next?

A. Develop a communications management plan

B. Perform a stakeholder analysis

C. Evaluate the risks

D. Escalate to the project sponsor

在为一个内部项目制定项目章程时,项目经理意识到一些职能经理的期望与另一些职能经理的期望相冲突,可能对项目产生负面影响。项目经理下一步该怎么做?

A.制定沟通管理计划

B.执行干系人分析

C.评估风险

D.上报给项目发起人

PMP答案解析:分析每个干系人可能的影响或支持,并把他们分类,以便制定管理策略。评估关键干系人对不同情况可能做出的反应或应对,以便策划如何对他们施加影响,提高他们的支持,减轻他们的潜在负面影响。

PMP参考答案:B

阅读本文的人还阅读了:
PMP的价值在哪?
PMP认证考试的报名条件?
PMP是什么?
PMP考试有什么科目?
PMP考试时间一年有几次?
PMP考试时间具体是什么?
PMP考试报名时间是什么?
PMP教材是什么?

留言讨论区
我也来说两句


获取更新

合作与联系

友情链接: PMP培训团购网 安徽成考网 建工团购网 项目管理者联盟 pmp百科 磨石建筑教育 SPC培训 企业管理培训 清晖PMP培训 光环国际 青岛旅行社
PMP团购导航
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
东北PMP团购
其他城市团购
远程PMP团购
PMP团购网
免费领PMP团购券