PMP考试每天一练-2019年PMP考试试题12
PMP考试试题一: The project manager is replaced during the execution phase. Management, customer and project team members are dissatisfied with the project’s communications methods What should the project manager do first? A.Update the communications management plan B.Consult the stakeholder register C.Create a project management information system D.Develop a stakeholder management plan 在项目执行阶段,项目经理被替换了。管理层、客户和项目团队成员都对项目的沟通方式感到不满意。项目经理首先应该怎么做? A.更新沟通管理计划 B.查阅干系人登记册 C.创建项目管理信息系统 D.制定干系人管理计划 PMP答案解析:干系人对沟通方式不满意,应该更新沟通管理计划 PMP参考答案:A PMP考试试题二 A new integration project includes the delivery of an unreleased software product. What is the appropriate timeframe for defining testing methods for this software product? A.WHILE PREPARING THE QUALITY MANAGEMENT PLAN B.AT THE START OF INTEGRATION TESTING C.WHEN STARTING PERFORMANCE TESTING D.DURING THE FINAL CONSTRUCTION OF THE SOFTWARE PRODUCT 一个新的整合项目包括交付未发布的软件产品。确定该软件产品测试方法的适当时间范围是什么? A.准备质量管理计划的同时 B.在整合测试开始时 C.开始性能测试时 D.在最终完成软件产品期 PMP答案解析:题目在问:什么时间确定软件产品的测试方法?应该在规划质量管理过程时 PMP参考答案:A |