PMP考试每天一练-2019年PMP考试试题1
PMP考试试题一: A new warehouse is ready for operations. Before operations begin, the project manager must prepare the final project report. To what should the project manager refer? A. Lessons learned, project charter, and work breakdown structure (WBS) B. Project baselines, accepted deliverables, and earned value (EV) C. Checklists, responsibility assignment matrix(RAM), and risk management plan D. Accepted deliverables, lessons learned, and transition criteria 一个新的仓库准备好运营。运营开始之前,项目经理必须准备最终项目报告。项目经理应该查阅哪些文件? A.经验教训、项目章程和工作分解结构(WBS) B.项目基准、已验收的可交付成果和挣值(EV) C.核对表、责任分配矩阵(RAM)和风险管理计划 D.已验收的可交付成果、经验教训和移交标准 PMP答案解析:四个答案中,做为项目转入运营之前的最终报告,最好的内容是答案D PMP参考答案:D PMP考试试题二 Before the stakeholder meeting. What communication method should the project manager use to obtain key stakeholder approval of the project management plan? A.Email B.Interactive C.Pull D.push 在干系人会议之前,项目经理应使用什么沟通方式获得干系人对项目管理计划的认可? A.电子邮件 B.交互式沟通 C.拉式沟通 D.推式沟通 PMP答案解析:交互式沟通 PMP参考答案:B |