PMP考试试题一:

A new warehouse is ready for operations. Before operations begin, the project manager must prepare the final project report. To what should the project manager refer?

A. Lessons learned, project charter, and work breakdown structure (WBS)

B. Project baselines, accepted deliverables, and earned value (EV)

C. Checklists, responsibility assignment matrix(RAM), and risk management plan

D. Accepted deliverables, lessons learned, and transition criteria

一个新的仓库准备好运营。运营开始之前,项目经理必须准备最终项目报告。项目经理应该查阅哪些文件?

A.经验教训、项目章程和工作分解结构(WBS)

B.项目基准、已验收的可交付成果和挣值(EV)

C.核对表、责任分配矩阵(RAM)和风险管理计划

D.已验收的可交付成果、经验教训和移交标准

PMP答案解析:四个答案中,做为项目转入运营之前的最终报告,最好的内容是答案D

PMP参考答案:D

PMP考试试题二

Before the stakeholder meeting. What communication method should the project manager use to obtain key stakeholder approval of the project management plan?

A.Email

B.Interactive

C.Pull

D.push

在干系人会议之前,项目经理应使用什么沟通方式获得干系人对项目管理计划的认可?

A.电子邮件

B.交互式沟通

C.拉式沟通

D.推式沟通

PMP答案解析:交互式沟通

PMP参考答案:B

阅读本文的人还阅读了:
PMP考试有什么科目?
PMP考试三个月来得及吗?
广州PMP考试地点
PMP考试报名资格怎么审查?
PMP认证培训怎么选机构?
PMP考试地点在哪里?
PMP考试费用是多少?
PMP考试时间是什么?

留言讨论区
我也来说两句


获取更新

合作与联系

友情链接: PMP培训团购网 安徽成考网 健身教练培训 项目管理者联盟 天津坦途教育网 磨石建筑教育 SPC培训 光环国际 青岛旅行社 湖南自考
PMP团购导航
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
东北PMP团购
其他城市团购
远程PMP团购
PMP团购网
免费领PMP团购券