PMP考试每天一练-2018年PMP考试试题159
PMP考试试题一: A company's director is concerned with project failure and hires a project manager to determine where additional funding should be allocated to ensure success. For what activity should the project manager recommend additional funding? A.Warranty work B.Rework C.Testing D.Scrap 公司董事担心项目失败,并聘用一名项目经理,以确定应分配额外的资金确保项目成功。项目经理应建议对哪项活动分配额外资金? A.保修工作 B.返工 C.测试 D.废料 PMP答案解析:本题点在于质量成本。预防胜于检查,测试属于质量成本中的一致性成本,其它三项都属于非一致性成本 PMP参考答案:C PMP考试试题二 Which of the following techniques attempts to balance resource requirements by rescheduling specific activities? A.Scheduling compression B.Leveling C.Smoothing D.Adjusting leads and lags 下列哪一项技术尝试通过重新安排特定活动的进度以便平衡资源需求? A.进度压缩 B.平衡 C.环节 D.调整时间提前量和滞后量 PMP答案解析:资源平衡 PMP参考答案:B |